Heart 2 Home: Kuester Extreme Makeover

Just a few more days and our extreme build will kick off! A crazy couple of weeks… and then a new home for a deserving family.

Here is a link to a great story (written by my former college professor- Bob Walz, ABC4 News) about the family and their compelling story…

http://www.abc4.com/news/local/story/Heart-2-Home-to-rebuild-home-for-a-devastated/3FpEGMGa60qZH0COtINJbQ.cspx

Here is the Schedule…
UTAH HOME MAKEOVER KUESTERS

Monday, April 12, 2010
7AM DEMOLITION, excavation of home
9AM FOOTING
1PM FOUNDATION(inc.window wells,pumps)
5pm DAMPPROOFING/WINDOW WELLS

Tuesday, April 13, 2010
7AM UNDERGROUND PLUMBING and INSPECTION
Trusses Delivered
8:45AM BACKFILL INSIDE ONLY
9AM FLATWORK (BASEMENT FLOOR)
9:30AM FRAMING MATERIALS (DELIVERY)
4PM FRAMING LABOR

Wednesday, April 14, 2010
7AM HVAC(1- furnace and ac unit)
7AM FIREPLACE
9AM TUBS , ELECTRICAL
12PM PLUMBING
12PM BACKFILL OUTSIDE

Thursday, April 15, 2010
7AM ROOFING
7AM 4-WAY INSPECTION
10AM STOCK DRYWALL
10AM INSULATION
10AM SIDING
12PM DRYWALL TAPING & TEXTURING
1PM DRYWALL
3PM BRICK DELIVERY/ LABOR

Friday, April 16, 2010
7AM SOFFIT/FACIA
12PM MARBLE SURROUNDS
3PM WOOD AND TILE FLOORS
3PM FINISH TRIM MATERIALS, CABINET INSTALL

Saturday, April 17, 2010
7AM EXTERIOR FLATWORK
7AM FINISH LABOR
10AM PAINT
12PM LIGHTING

Monday, April 19, 2010
7AM FINISH ELECTRICAL
7AM GARAGE DOORS
7AM LANDSCAPING
7AM COUNTERTOPS (CORIAN)

Tuesday, April 20, 2010
7AM FINISH PLUMBING
10AM FINISH HEATING
10AM APPLIANCES (UPSTAIRS)
10AM FLOORING

Wednesday, April 21, 2010
1PM HARDWARE/MIRRORS/ ETC…

Thursday, April 22, 2010
7AM CLEANING
10AM INTERIOR DESIGN AND SET UP

Friday, April 23, 2010
FINISH DECORATING AND CLEANUP
5PM WELCOME HOME KUESTERS FAMILY

We are still in need of Volunteers and donations… go here to help!

http://www.heart2homefoundation.org/

Watch for pictures and updates to come!! This really is really too much fun.